Decay Solenoid Inversion v1.5 - Nebrensky, Henry, 08 December 2011 15:24

 
1
Reversal of MICE Decay Solenoid Polarity 
2

    
3
Henry Nebrensky
4
v1.5
5

    
6
We would like to reverse the polarity of the Decay Solenoid, as we would like to know two things:
7

    
8
- is keeping the current in the same direction behind the different speeds we see for electrons and positrons?
9
- (if so) does it affect the number of good muons we get?
10

    
11
There are two steps to this:
12

    
13
1) we need to confirm the DS can be run at all with reversed polarity, which really means doing it
14
2) a series of data runs with the different polarities; at least one e/pi/mu setting  and one mu setting
15

    
16
For 1): although we do not anticipate any difficulties, the first time we do this we also have to label up all the cables and similar tasks, so it will take much longer than normal to make the change 
17
For 2): we need to look at two DS polarities relative to two beamline polarities, implying 5 sets of runs separated by 4 electrical interventions (30-60 mins each) (for which we need an authorised person). Changing DS polarity means stopping and starting the current - i.e. significant quench risk.
18

    
19
Thus I estimated we would need at least a day and a half at the end of the December run.
20

    
21
Comments/options: 
22
a) 1) really needs to be done soon and any issues found and addressed, else we waste a lot of time on false plans.
23
   I've checked Martin Hughes is available (*at present* only authorised person): _morning only_ Fri 16th, and Mon. 19th.
24
   Both Stewart Greenall (new Hall manager) and Mike Courthold could be authorised - not clear about timescale for that to take effect.
25

    
26
b) we could leave 2) until February - indeed probably should leave it until new quench detector available for ramping the DS
27

    
28
c) Week after Dec. run has been reserved in bulk for ISIS access to substation. *might* be able to run 2) on one day, but unlikely. 
29
   1) is more likely - the DS warm-up can start after Monday.
30

    
31
Electrical work is already due to start on 19th, though we think it should still be possible to run into the DSA - we need to confirm this.
32
Present aim is to try the inversion and if possible take some data using DSA only on Monday 19th.
33

    
34
We could do something on 17/18, but have no shifter or BLOC scheduled, AND would need experts.
35

    
36
Not checked availability yet for 15th - how confident are we that everything would be done.
37

    
38

    
39
Questions:
40
 - any other effects we are testing for?
(2-2/2)