h1. Commissioning and Ops Scheduling meeting : 5/1/2016
2 1 Boyd, Steven
3 1 Boyd, Steven
To be held in CR10 in the ATLAS Building @ 15:30 pm 
4 1 Boyd, Steven
5 1 Boyd, Steven
Phone access :  ReadyTalk number 
6 1 Boyd, Steven
US 866-740-1260
7 1 Boyd, Steven
UK 0800-496-0576
8 1 Boyd, Steven
Swiss 0800-70-53-51
9 1 Boyd, Steven
Italy 800182592
10 1 Boyd, Steven
Access Code: 2155402
11 1 Boyd, Steven
12 1 Boyd, Steven
h2. Agenda:
13 1 Boyd, Steven
14 1 Boyd, Steven
* Review of tasks and activities identified at last meeting
15 1 Boyd, Steven
** test of the Q4 flush - take magnet to high current and see if it trips.
16 1 Boyd, Steven
** Temperature readout investigation/swap of Q4 / Q5 sensors (Henry)
17 1 Boyd, Steven
** Network reconfiguration for C&M : Document by Pierrick on changes are needed in the network configuration so that system owners
18 1 Boyd, Steven
understand the impact.
19 8 Boyd, Steven
** Talk to John about conventional magnet cooling system flush   
20 8 Boyd, Steven
** Henry/Pierrick to come up with a design for the Q456 drip trays + finish Q789 drip trays
21 8 Boyd, Steven
** Design for safe access to top of PRY / Andy
22 1 Boyd, Steven
* Upcoming activities : chaired by DC
23 1 Boyd, Steven
** [[WorkPlanJanuary2016|To-do list]] for Maintenance shutdown (January 2016)
24 4 Boyd, Steven
** "Operations calendar":https://www.google.com/calendar/embed?src=miceops%40gmail.com&ctz=Europe/London
25 1 Boyd, Steven
** Looking ahead
26 6 Boyd, Steven
*** ISIS run-up starts Feb 1
27 5 Boyd, Steven
*** Next user cycle : Feb 19th - March 25th
28 5 Boyd, Steven
*** Expect to take data from the last week of February (no channel magnets on, no DS). Initially plan to take data with
29 7 Boyd, Steven
 an empty absorber, but would like to change to LiH in early March.
30 9 Boyd, Steven
* AOB
31 1 Boyd, Steven
* Date of next meeting : January 12th