Commissioning and Ops Scheduling meeting : 5/1/2016

To be held in CR10 in the ATLAS Building @ 15:30 pm

Phone access : ReadyTalk number
US 866-740-1260
UK 0800-496-0576
Swiss 0800-70-53-51
Italy 800182592
Access Code: 2155402

Agenda:

  • Review of tasks and activities identified at last meeting
    • test of the Q4 flush - take magnet to high current and see if it trips.
    • Temperature readout investigation/swap of Q4 / Q5 sensors (Henry)
    • Network reconfiguration for C&M : Document by Pierrick on changes are needed in the network configuration so that system owners
      understand the impact.
    • Talk to John about conventional magnet cooling system flush
    • Henry/Pierrick to come up with a design for the Q456 drip trays + finish Q789 drip trays
    • Design for safe access to top of PRY / Andy
  • Upcoming activities : chaired by DC
    • To-do list for Maintenance shutdown (January 2016)
    • Operations calendar
    • Looking ahead
      • ISIS run-up starts Feb 1
      • Next user cycle : Feb 19th - March 25th
      • Expect to take data from the last week of February (no channel magnets on, no DS). Initially plan to take data with
        an empty absorber, but would like to change to LiH in early March.
  • AOB
  • Date of next meeting : January 12th