h1. Commissioning and Ops Scheduling meeting : 5/1/2016
2 1 Boyd, Steven
3 1 Boyd, Steven
To be held in CR10 in the ATLAS Building @ 15:30 pm 
4 1 Boyd, Steven
5 1 Boyd, Steven
Phone access :  ReadyTalk number 
6 1 Boyd, Steven
US 866-740-1260
7 1 Boyd, Steven
UK 0800-496-0576
8 1 Boyd, Steven
Swiss 0800-70-53-51
9 1 Boyd, Steven
Italy 800182592
10 1 Boyd, Steven
Access Code: 2155402
11 1 Boyd, Steven
12 1 Boyd, Steven
h2. Agenda:
13 1 Boyd, Steven
14 1 Boyd, Steven
* Review of tasks and activities identified at last meeting
15 1 Boyd, Steven
** test of the Q4 flush - take magnet to high current and see if it trips.
16 1 Boyd, Steven
** Temperature readout investigation/swap of Q4 / Q5 sensors (Henry)
17 1 Boyd, Steven
** Network reconfiguration for C&M : Document by Pierrick on changes are needed in the network configuration so that system owners
18 1 Boyd, Steven
understand the impact.
19 8 Boyd, Steven
** Talk to John about conventional magnet cooling system flush   
20 8 Boyd, Steven
** Henry/Pierrick to come up with a design for the Q456 drip trays + finish Q789 drip trays
21 8 Boyd, Steven
** Design for safe access to top of PRY / Andy
22 1 Boyd, Steven
* Upcoming activities : chaired by DC
23 1 Boyd, Steven
** [[WorkPlanJanuary2016|To-do list]] for Maintenance shutdown (January 2016)
24 4 Boyd, Steven
** "Operations calendar":https://www.google.com/calendar/embed?src=miceops%40gmail.com&ctz=Europe/London
25 1 Boyd, Steven
** Looking ahead
26 6 Boyd, Steven
*** ISIS run-up starts Feb 1
27 5 Boyd, Steven
*** Next user cycle : Feb 19th - March 25th
28 5 Boyd, Steven
*** Expect to take data from the last week of February (no channel magnets on, no DS). Initially plan to take data with
29 7 Boyd, Steven
 an empty absorber, but would like to change to LiH in early March.
30 9 Boyd, Steven
* AOB
31 1 Boyd, Steven
* Date of next meeting : January 12th
32 10 Boyd, Steven
33 10 Boyd, Steven
34 10 Boyd, Steven
h2. Minutes
35 10 Boyd, Steven
36 10 Boyd, Steven
Present: Holge, Craig, Pierrick, Mark T, Andy, John G, Victoria B, Henry, Ed, Colin, Josef, Steve, Ken
37 10 Boyd, Steven
38 10 Boyd, Steven
* Review of tasks and activities:
39 10 Boyd, Steven
40 10 Boyd, Steven
** Q4 was flushed and operated and maximum current. It didn't trip (which doesn't necessarily mean that the trip problem was fixed, just that we haven't harmed Q4).
41 10 Boyd, Steven
** Pierrick checked the temperature readout for Q5/6 which appears to be swapped. He believes that the problem is in the addressing, and
42 10 Boyd, Steven
this can be fixed in software. He's implemented a fix, but hasn't tested it yet.
43 10 Boyd, Steven
** Pierrick has written up a document for the changes to the network for C&M but has not distributed it yet. He thinks that the work will 
44 10 Boyd, Steven
take place from Jan 15th - Jan 31st.
45 10 Boyd, Steven
** John has already started flushing the other conventional magnets but has run into problems with air blocks in the line. He thinks he has
46 10 Boyd, Steven
a work around for this which he'll look at this week. 
47 10 Boyd, Steven
** Henry has come up with a design for the conventional magnet drip trays and will talk to John about it on Thursday.
48 10 Boyd, Steven
** Andy and John are on discussions about a way to make the top of the PRY safe. At present the idea is to install some mesh to
49 10 Boyd, Steven
stop people falling into the PRY from above with a N-S clip-on bridge, but this needs some development. Hope to have this in place by
50 10 Boyd, Steven
the end of the month. Josef has used a Scottish company which manufactures bespoke bridges like this and will talk to Andy.
51 10 Boyd, Steven
52 10 Boyd, Steven
* Activities this month. 
53 10 Boyd, Steven
54 10 Boyd, Steven
** The operations calendar has been updated with activities that are planned for this month.
55 10 Boyd, Steven
** There was discussion concerning whether SSD can be manually realigned before the Feb data-taking or between the Feb
56 10 Boyd, Steven
and April user cycles. It was clear that we wouldn't decide in this meeting
57 10 Boyd, Steven
58 10 Boyd, Steven
*** *Action Item* : Colin will organise a meeting for Thursday morning to consider this issue.