Project

General

Profile

Apr15-RLSRMPB-Prep

16 April 2015
09:00-09:45 RLSR closed session – introduction
09:45-10:15 Project overview: 01-2015-04-16-Long.pptx K. Long 20' + 10'
10:15-12:45 RLSR presentations & questions
Schedule to completion, project risks and overview of critical interfaces: 02-2015-04-16-Preece.ppt R. Preece 30' + 10'
Re-baselined deliverables, critical decision points and status of US deliverables: 03_Palmer_RLSR_R3.pptx M. Palmer 30' + 10'
UK financial plan, risks: 04-Slides-grant-2015-4-16_RLSR.pptx A. Grant 20' + 10'
US financial plan, risks: 05-April-2015-US-Project-Plan.pptx P. Garbincius 20' + 10'
Unscheduled 150’ - 140’ = 05'
12:45-13:15 Lunch
13:15-14:00 RLSR closed session – critical findings
14:00-15:30 Step IV, commissioning, operations and control
Step IV commissioning and operations planning; overview: 06-Operations_MPBTalk_Apr2015_Draft_v3.pdf S. Boyd 20' + 5'
MICE Muon Beam and MICE channel optics and commissioning plan J. Pasternak 15' + 5'
Step IV measurements and analysis planning: 08-Step-IV-Analysis.pdf C. Rogers 15' + 5'
Controls and monitoring: mpbSp15_hanlet_v2.pdf P. Hanlet 15' + 5'
Unscheduled 90’ - 85’ = 5'
15:30-16:00 Closed session
16:00-17:30 Reconstruction, simulation and data flow
Software, computing and data processing; overview: 10-computing-mpb-apr2015.pdf D. Rajaram 15' + 5'
Reconstruction; online, offline and batch: 11-MAUS-Update-v4.pptx A. Dobbs 15' + 5'
Simulation and configuration management: 12-SimulationConfigurationManagement.pdf R. Bayes 10' + 5'
Data flow: from front-end boards to automatic batch processing: Online_Report_YK.pdf Y. Karadzhov 10' + 5'
MICE computing infrastructure: 14-Franchini_MPBApril2015_infrastructure.pdf P. Franchini 10' + 5'
Unscheduled 90’ - 85’ = 5'
17:30-18:00 Closed session, report writing
18:00 Adjourn
17 April 2015
09:00-10:30 Cooling-demonstration integration, SC magnets and RF
Focus-coils, absorbers and LH2 system for Step IV: 15-MPB_18-04-15_AFC_LH2.ppt S. Watson 20' + 10'
Cavity modules and test programme, PRY and spectrometer solenoids: 16-MPB_4-15_v1.pptx A. Bross 20' + 10'
RF-power distribution: 17-RF_Status_Update-5-Apr-2015.pptx K. Ronald 20' + 10'
Unscheduled 90’ - 90’ = 0'
10:30-11:30 Closed session, report writing
11:30-12:00 Close-out with MICE management
12:00-13:00 Lunch
13:00 Adjourn for report writing

Backup presentations:

  • To be posted.

Back

01-2015-04-16-Long.pptx (6.72 MB) Long, Kenneth, 12 April 2015 09:30

06-Operations_MPBTalk_Apr2015_Draft.pdf (218 KB) Long, Kenneth, 12 April 2015 09:34

12-SimulationConfigurationManagement.pdf (107 KB) Long, Kenneth, 12 April 2015 09:39

17-RF_Status_Update-Apr-2015-s.pptx (1.57 MB) Long, Kenneth, 12 April 2015 09:40

08-Step-IV-Analysis.pdf (107 KB) Rogers, Chris, 14 April 2015 11:20

06-Operations_MPBTalk_Apr2015_Draft_v2.pdf (239 KB) Boyd, Steven, 14 April 2015 13:44

MPB_4-15_v1.pptx - Cavity modules and test programme, PRY and spectrometer solenoids (12.8 MB) Bross, Alan, 14 April 2015 13:44

04-Slides-grant-2015-4-16_RLSR.pptx (724 KB) Long, Kenneth, 14 April 2015 14:56

16-MPB_4-15_v1.pptx (12.8 MB) Long, Kenneth, 14 April 2015 14:57

15-MPB_18-04-15_AFC_LH2.ppt (1.05 MB) Watson, Steve, 14 April 2015 16:03

Online_Report_YK.pdf (376 KB) Karadzhov, Yordan, 14 April 2015 23:03

14-Franchini_MPBApril2015_infrastructure.pdf (2.32 MB) Franchini, Paolo, 15 April 2015 00:22

SimulationConfigurationManagement_v2.pdf (107 KB) Bayes, Ryan, 15 April 2015 11:02

11-MAUS-Update-v4.pptx (762 KB) Dobbs, Adam, 15 April 2015 11:44

11-MAUS-Update-v4.pdf (1.27 MB) Dobbs, Adam, 15 April 2015 11:44

17-RF_Status_Update-3-Apr-2015.pptx (1.57 MB) Ronald, Kevin, 15 April 2015 12:43

17-RF_Status_Update-3-Apr-2015.pptx (1.57 MB) Ronald, Kevin, 15 April 2015 12:50

17-RF_Status_Update-4-Apr-2015.pptx (1.57 MB) Ronald, Kevin, 15 April 2015 12:58

mpbSp15_hanlet_v2.pdf (6.72 MB) Hanlet, Pierrick, 15 April 2015 13:06

06-Operations_MPBTalk_Apr2015_Draft_v3.pdf (362 KB) Boyd, Steven, 15 April 2015 13:22

17-RF_Status_Update-5-Apr-2015.pptx (1.57 MB) Ronald, Kevin, 15 April 2015 14:59

Beam_physics_MPB0415.pdf (551 KB) Pasternak, Jaroslaw, 15 April 2015 16:41

Slides-grant-2015-4-16_RLSR.pptx (378 KB) Grant, Alan, 15 April 2015 17:44

05-April-2015-US-Project-Plan.pptx (452 KB) Preece, Roy, 15 April 2015 18:04

02-2015-04-16-Preece.ppt (8.94 MB) Preece, Roy, 15 April 2015 18:15

10-computing-mpb-apr2015.pdf (394 KB) Rajaram, Durga, 15 April 2015 18:40

03_Palmer_RLSR_R2.pptx (12.5 MB) Palmer, Mark, 15 April 2015 19:18

03_Palmer_RLSR_R3.pptx (45.7 MB) Palmer, Mark, 16 April 2015 07:44

17-RF_Status_Update-8-Apr-2015.pptx (1.16 MB) Ronald, Kevin, 16 April 2015 18:05