ISIS Run 2016/05

Days Shifter Measurement Measurement Coordinator Report
24-28 February Rogers Emittance reduction Rogers 2017-02-28_physics-shifter

ISIS Run 2016/04

Days Shifter Measurement Measurement Coordinator Report
19-22 November Rogers Emittance reduction setting 2016-04 1.3 Rogers 2016-11-19_physics-shifter
28-1 December Rogers Emittance reduction setting 2016-04 1.2 Rogers 2016-11-28_physics-shifter
3-4 December Drielsma Emittance reduction setting 2016-04 1.2 Rogers Physics_shift_2016-12-03
5-8 December Drielsma, Liu Emittance reduction setting 2016-04 1.5 Rogers Physics_shift_2016-12-05
9-12 December Liu, Drielsma Emittance reduction setting 2016-04 1.7 Rogers Physics_shift_2016-12-09
13-16 December Drielsma, Liu Emittance reduction setting 2016-04 2.4a Rogers Physics_shift_2016-12-13

ISIS Run 2015/04

Nb: ISIS user run finishes 25 March, machine physics is expected on 26th and 27th. Maintenance day is 2nd March.

Days Shifter Measurement Measurement Coordinator Report
17 February Scott Wilbur
23-27 February Francois Drielsma TOF calib., alignment D. Rajaram, F. Drielsma Physics_shift_2016-02-27
28 Feb-3 March
4-9 March
10-14 March
15-19 March John Nugent Lithium Hydride scattering John Nugent
20-24 March
25(-27) March

ISIS Run 2015/03

3rd November - 18th December

Data taking will run from 3rd December - 18th December; there will be additional physics shifts during the mock data runs.

Days Shifter Measurement Measurement Coordinator Report
24 November Scott Wilbur
3-8 December Sophie Middleton/Chris Rogers/John Nugent
9-13 December Sophie Middleton/Chris Rogers/Ryan Bayes?
14-18 December Sophie Middleton/Chris Rogers/John Nugent

ISIS Run 2015/02

8th September - 16th October
No shifts were filled during this period

ISIS Run 2015/01

2 June - 4 July, followed by a break, followed by 14 July - 24 July

Days Shifter Measurement Measurement Coordinator Report
2-6 June Ryan Bayes Q1-3 scan J. Pasternak 2 June
7-11 June Paolo Franchini TOF calibration J. Pasternak 12 June
12-16 June Chris Heidt TOF calibration and Tracker Timing
17-21 June Chris Rogers Tracker Timing E. Overton physics_shift_2015-06-17
Tracker Timing, TOF Calib physics_shift_2015-06-18
22-26 June Paolo Franchini Tracker studies, TOF Calib, Diffuser studies 26 June
27 June - 1 July Chris Hunt Physics_shift_2015-07-01
2 - 5 July Francois Drielsma TOF calibration D. Rajaram Physics_shift_2015-07-05
14 - 18 July Francois Drielsma Reference runs R. Bayes Physics_shift_2015-07-18
19 - 23 July John Nugent Physics_shift_19_07_2015
24 - 24 July John Nugent Rogers_analysis_2015-07-24

ISIS Run 2015/04

16th February - 1st April

Previous Shifts